2. Plan-to-Plan
The Plan-to-Plan is how the MPC Chief (MPCC) commands the planning effort. It is a 30-80% solution that organizes how the MPC will complete the planning work, prevents uncontrolled planning, and ensures the Tactical Mission Plan (TMP) develops in a deliberate, synchronized manner.
2.1. Outline MPOs/MPTsβ
Similar to how TOs/TTs guide a Mission Element's (ME) execution, the MPCC must create Mission Planning Objectives (MPOs) and Mission Planning Tasks (MPTs) to effectively guide the MPC's planning.
- MPOs describe the required planning end states that must exist for the TMP to be considered complete and executable.
- MPTs are discrete planning actions assigned to planning LOEs to achieve an MPO.
2.1.1. Develop Planning Objectivesβ
- Divide the required planning work into functional objectives as MPOs
NOTE: Ideally, most of the MPOs align with the functional planning LOEs
- MPO characteristics:
- Define required planning end conditions
- Are outcome-focused and assessable
- Status is determined by MPT completion and integration
- Have a tangible output artifact
- Each MPO must have tangible output or products
## MISSION PLANNING OBJECTIVES (MPOs)
- MPO-1: Perform FMA-C to identify MRT-C and KT-C
- MPO-2: Develop the CVA/H Deployment Plan
- MPO-3: Develop Host Agent Deployment + Data Collection Plans
- MPO-4: Identify and Characterize Potential Threats
- MPO-5: Develop the Threat Hunt Plan
- MPO-6: Develop the Execution Framework
- MPO-7: Develop Communication Contracts
- MPO-8: Establish Logistics Coordination
- MPO-9: Provide Intelligence Support to Planning
- MPO-10: Conduct the ROC Drill and Refine the Plan
- MPO-11: Integrate and Finalize the Tactical Mission Plan (TMP)
2.1.2. Develop Planning Tasksβ
- For each MPO, outline the discrete tasks that are required for the MPC to achieve it
- MPT characteristics:
- They outline the planning work that must be done to achieve the supported MPO
- Are directly assigned to planning LOEs
- Produce or update a tangible planning output
- Directly support one or more MPOs
## MISSION PLANNING OBJECTIVES (MPOs)
- MPO-1: Perform FMA-C to identify MRT-C and KT-C
- MPT-1.1: Define the supported mission's purpose, method, and goals
- MPT-1.2: Identify METs, MEFs, and associated TCAs
- MPT-1.3: Identify critical information flows enabling MEFs
- MPT-1.4: Identify Unacceptable Losses (ULs) and associated cyber hazards
- MPT-1.5: Identify and distinguish KT-C and MRT-C assets
- MPT-1.6: Prioritize MRT-C and KT-C assets by mission impact
- MPO-2: Develop the CVA/H Deployment Plan
- MPT-2.1: Collect and validate logical and physical network architecture
- MPT-2.2: Identify MRT-C boundaries, aggregation points, and monitoring choke points
- MPT-2.3: Identify infrastructure device capabilities and integration constraints
- MPT-2.4: Identify physical installation requirements and hardware needs
- MPT-2.5: Determine DIP Sensor monitoring methods and optimal placement strategy
- MPT-2.6: Develop the DIP Sensor Deployment Plan and translate to executable TTs
- MPO-3: Develop Host Agent Deployment + Data Collection Plans
- MPT-3.1: Analyze targeted threat TTPs to determine required host data sources
- MPT-3.2: Map required data components to CVA/H capabilities and identify gaps
- MPT-3.3: Identify endpoints and log sources requiring collection configuration
- MPT-3.4: Develop Host Agent deployment, log forwarding, and data collection plans
- MPT-3.5: Validate collection coverage across MRT-C assets
- MPT-3.6: Translate deployment and collection plans into executable TTs
- MPO-4: Identify and Characterize Potential Threats
- MPT-4.1: Identify mission-relevant threat actors and associated capabilities
- MPT-4.2: Identify relevant adversary TTPs, tools, infrastructure, and indicators
- MPT-4.3: Develop adversary concept sketch targeting MRT-C and KT-C
- MPT-4.4: Assess MLECOA and MDECOA against mission dependencies
- MPT-4.5: Identify detection and response implications
- MPT-4.6: Produce threat brief to inform planning and execution
- MPO-5: Develop the Threat Hunt Plan
- MPT-5.1: Develop prioritized hunt hypotheses based on threat COAs
- MPT-5.2: Identify required data sources and validate availability
- MPT-5.3: Develop detection logic and analytic approach
- MPT-5.4: Identify investigative pivots and escalation criteria
- MPT-5.5: Sequence hunt activities by priority
- MPT-5.6: Translate hunt plan into executable TTs
- MPO-6: Develop the Execution Framework
- MPT-6.1: Define execution LOEs grouped by functional area
- MPT-6.2: Define MINFOR crew positions and assign roles
- MPT-6.3: Assign TTs to execution LOEs
- MPT-6.4: Sequence TTs and resolve task dependencies
- MPT-6.5: Define execution phases and transition criteria
- MPT-6.6: Develop integrated execution timeline with triggers and decision points
- MPO-7: Develop Communication Contracts
- MPT-7.1: Identify required stakeholders
- MPT-7.2: Define supported/supporting relationships
- MPT-7.3: Establish communication methods and redundancies
- MPT-7.4: Define reporting formats, frequency, and escalation thresholds
- MPT-7.5: Establish battle rhythm events
- MPT-7.6: Document communication contracts in the TMP
- MPO-8: Establish Logistics Coordination
- MPT-8.1: Coordinate personnel movement, access, and facility support
- MPT-8.2: Confirm equipment shipping, installation, and sustainment requirements
- MPT-8.3: Validate power, rack space, environmental, and physical security support
- MPT-8.4: Coordinate network access approvals and authorizations
- MPT-8.5: Establish logistics POCs
- MPT-8.6: Document logistics constraints in the TMP
- MPO-9: Provide Intelligence Support to Planning
- MPT-9.1: Identify PIRs aligned to mission objectives
- MPT-9.2: Collect and analyze mission-relevant threat intelligence
- MPT-9.3: Refine MLECOA and MDECOA assessments
- MPT-9.4: Identify intelligence-driven detection priorities
- MPT-9.5: Collect and track RFIs generated by the MPC
- MPT-9.6: Integrate intelligence updates into planning products
- MPO-10: Conduct the ROC Drill and Refine the Plan
- MPT-10.1: Execute a full ROC drill by phase, LOE, and crew position
- MPT-10.2: Validate task sequencing, triggers, dependencies, and decision points
- MPT-10.3: Identify friction points, timing conflicts, and resource contention
- MPT-10.4: Identify unresolved assumptions impacting execution
- MPT-10.5: Develop contingency TTs tied to assumption failure and adverse conditions
- MPT-10.6: Update the execution framework based on ROC findings
- MPO-11: Integrate and Finalize the Tactical Mission Plan (TMP)
- MPT-11.1: Consolidate MPC outputs into a unified TMP framework
- MPT-11.2: Validate consistency across LOEs, TTs, phasing, triggers, and contingencies
- MPT-11.3: Develop and deliver the Mission Brief (ME3PC2 format) for Mission Commander approval
- MPT-11.4: Incorporate Mission Commander feedback and approval decisions
- MPT-11.5: Finalize the TMP in the format required by the final approval authority
- MPT-11.6: Produce the execution-ready TMP package for the Mission Element
2.2. Outline Planning LOEsβ
Planning Lines of Effort (LOEs) organize the MPC's work into functional areas and:
- Prevent overlap and duplication of effort
- Provide clear ownership of planning work
- Enable parallel planning
- Allow the MPCC to track progress and integration
- Are assigned MPTs in order to collectively achieve MPOs.
2.2.1. Define Planning LOEsβ
- Define planning LOEs based on the mission and required MPOs
- Planning LOEs should:
- Reflect functional groupings of planning work
- Enable parallel development and later integration
- Each planning LOE must have:
- A single accountable lead
- Defined integration touchpoints
- A clearly defined functional focus
- Identified supporting members
- Planning LOEs may also be formed/disbanded based on specific points within the MPC timeline
## PLANNING LOEs
- FMA-C
- CVA/H Deployment
- Data Collection
- Hunt Planning
- Intel Support
- Logistics
2.2.2. Assign MPTs to LOEsβ
- Assign each MPT to a specific LOE and ensure:
- MPTs are distributed logically across LOEs by function area
- Each MPT maps to exactly one LOE and at least one MPO
- Cross-LOE dependencies are identified early
- Integration requirements are visible
- Workload is balanced
NOTE: If an MPT does not have clear LOE ownership, planning accountability is lost
## PLANNING LOEs / MPT ASSIGNMENT
- LOE: FMA-C
- [ ] MPT-1.1
- [ ] MPT-1.2
- [ ] MPT-1.3
- [ ] MPT-1.4
- [ ] MPT-1.5
- [ ] MPT-1.6
- LOE: CVA/H Deployment
- [ ] MPT-2.1
- [ ] MPT-2.2
- [ ] MPT-2.3
- [ ] MPT-2.4
- [ ] MPT-2.5
- [ ] MPT-2.6
- LOE: Intel Support
- [ ] MPT-4.1
- [ ] MPT-4.2
- [ ] MPT-4.3
- [ ] MPT-4.4
- [ ] MPT-4.5
- [ ] MPT-4.6
- [ ] MPT-9.1
- [ ] MPT-9.2
- [ ] MPT-9.3
- [ ] MPT-9.4
- [ ] MPT-9.5
- [ ] MPT-9.6
2.3. Establish the MPC Timelineβ
The MPCC must impose time discipline on the planning effort and define the planning window from mission receipt to execution-ready TMP.
A structured timeline and battle rhythm:
- Forces convergence
- Prevents scope creep
- Protects integration and ROC time
- Ensures the TMP is mature before Commander approval
- Identify the major MPC timeline anchors first:
- MPC In-Brief / Kick-Off
- Formal start of structured planning
- Confirms mission understanding, MPOs/MPTs, LOEs, timeline, and expectations
- Establishes planning priorities and suspenses
- "How Goes It" (HGI) Checks
- Structured progress reviews led by the MPCC
- Assess MPO status and tangible MPT outputs
- Identify cross-LOE friction and reset priorities
- Enforce timeline discipline
- LOE Integration Points
- Consolidate LOE outputs into TMP structure
- Resolve cross-LOE conflicts before ROC
- "Good Idea Cut-Off Line" (GICL)
- Predetermined point where major plan changes are no longer accepted
- Protects stability prior to ROC
- After GICL, only risk-driven corrections are allowed
- ROC Drill
- Full table-top of the plan by phase, LOE, and crew position
- Validates sequencing, triggers, dependencies, and contingencies
- Identifies execution friction prior to Mission Commander brief
- Mission Commander Brief
- Formal presentation of the completed plan (SMEAC/ME3PC2 format)
- Confirms command approval, risk acceptance, and decision authorities
- Product Delivery
- Final execution-ready TMP package staged for the Mission Element
- All annexes, task matrices, and supporting products included
- MPC In-Brief / Kick-Off
- Identify non-GICL "lock points":
- MPO/MPT freeze (changes require MPCC approval)
- LOE deliverable cutoffs (integration protected time)
- Assumption/RFI cutoff for planning (late RFIs become contingencies)
- Outline all other important timeline events affecting the MPC, such as:
- Unique task/deliverable deadlines
- Scheduled Intel update briefs
- Administrative events
NOTE: The ROC drill must occur with sufficient time remaining to fix deficiencies.